gsd_state_version: 1.0
|
|
milestone: v1.0
|
|
milestone_name: milestone
|
|
status: verifying
|
|
stopped_at: Completed 01-02-PLAN.md
|
|
last_updated: "2026-03-29T23:42:10.010Z"
|
|
last_activity: 2026-03-29
|
|
progress:
|
|
total_phases: 10
|
|
completed_phases: 1
|
|
total_plans: 2
|
|
completed_plans: 2
|
|
percent: 0
|
|
---
|
|
|
|
# Project State
|
|
|
|
## Project Reference
|
|
|
|
See: .planning/PROJECT.md (updated 2026-03-29)
|
|
|
|
**Core value:** Agents produce actionable multi-leg options recommendations with transparent, educational reasoning
|
|
**Current focus:** Phase 01 — Tradier Data Layer
|
|
|
|
## Current Position
|
|
|
|
Phase: 2
|
|
Plan: Not started
|
|
Status: Phase complete — ready for verification
|
|
Last activity: 2026-03-29
|
|
|
|
Progress: [░░░░░░░░░░] 0%
|
|
|
|
## Performance Metrics
|
|
|
|
**Velocity:**
|
|
|
|
- Total plans completed: 0
|
|
- Average duration: -
|
|
- Total execution time: 0 hours
|
|
|
|
**By Phase:**
|
|
|
|
| Phase | Plans | Total | Avg/Plan |
|
|
|-------|-------|-------|----------|
|
|
| - | - | - | - |
|
|
|
|
**Recent Trend:**
|
|
|
|
- Last 5 plans: -
|
|
- Trend: -
|
|
|
|
*Updated after each plan completion*
|
|
| Phase 01 P01 | 3min | 2 tasks | 2 files |
|
|
| Phase 01 P02 | 4min | 2 tasks | 9 files |
|
|
|
|
## Accumulated Context
|
|
|
|
### Decisions
|
|
|
|
Decisions are logged in PROJECT.md Key Decisions table.
|
|
Recent decisions affecting current work:
|
|
|
|
- [Roadmap]: Phases 2, 3, 4 can run in parallel after Phase 1 (all depend only on Tradier data layer)
|
|
- [Roadmap]: SVI volatility surface isolated in its own phase (Phase 5) due to highest implementation risk
|
|
- [Roadmap]: All deterministic math in Phase 2 as standalone module before any agents consume it (critical pitfall mitigation)
|
|
- [Roadmap]: Tastytrade streaming deferred to Phase 10 as enhancement; batch pipeline uses Tradier REST throughout
|
|
- [Phase 01]: Session cache stores OptionsChain objects keyed by symbol:min_dte:max_dte
|
|
- [Phase 01]: Dual return pattern: string for LLM tools, dataclass for computation modules
|
|
- [Phase 01]: Tradier is sole vendor for options_chain category (no fallback yet)
|
|
- [Phase 01]: Options @tool functions convert list results to comma-separated strings for LLM readability
|
|
|
|
### Pending Todos
|
|
|
|
None yet.
|
|
|
|
### Blockers/Concerns
|
|
|
|
- Historical IV data endpoint for IV Rank (52-week history) needs validation during Phase 1/3 planning
|
|
- **Python >=3.11** is the project baseline (see `pyproject.toml` and `.planning/PROJECT.md`); required for the community **tastytrade** SDK used in Phase 10 — use a single venv (e.g. `uv venv --python 3.13`) for the whole repo; no separate “Phase 10 only” interpreter is required if the environment already meets >=3.11
|
|
- Tradier sandbox vs production Greeks fidelity unknown until Phase 1 implementation
|
|
|
|
## Session Continuity
|
|
|
|
Last session: 2026-03-29T23:38:01.718Z
|
|
Stopped at: Completed 01-02-PLAN.md
|
|
Resume file: None
|